- Project Integration Management knowledge area includes processes integrative by nature to all the other knowledge areas.
- This knowledge area has processes in all the Process Groups. This knowledge area is useful in making decisions when there are competing project objectives.
- The project / phase gets initiated through Develop Project Charter process and gets closed in Close Project or Phase process , both part of this knowledge area.
- The following are the processes in this knowledge area:
-> Develop Project Charter
-> Develop Project Management Plan
-> Direct and Manage Project Work
-> Monitor and Control Project Work
-> Perform Integrated Change Control
-> Close Project or Phase
- The following are the most important outputs from this knowledge area:
-> Project Charter – Initiating
-> Project Management Plan – Planning
- Project Management Plan is the master plan document that has the subsidiary plans from other knowledge areas integrated within.

Match the Following

1. Develop Project Charter - a. PM Plan
2. Develop Project Management Plan - b. Project Charter
3. Direct and Manage Project Work - c. Change Requests
4. Monitor and Control Project Work - d. Deliverables
5. Perform Integrated Change Control - e. Lessons Learnt
6. Close Project or Phase – f. Rejected Changes

Match the Following (Answers)

1. Develop Project Charter - b. Project Charter
2. Develop Project Management Plan - a. PM Plan
3. Direct and Manage Project Work - d. Deliverables
4. Monitor and Control Project Work - c. Change Requests
5. Perform Integrated Change Control - f. Rejected Changes
6. Close Project or Phase – e. Lessons Learnt