Introduction


- Project Scope Management knowledge area includes processes related to dealing with project and product scope.
- This knowledge area has processes in Planning as well as Monitoring and Controlling Process Groups. This knowledge area is useful in determining the project inclusions and exclusions.
- Scope Baseline includes approved version of Scope Statement, WBS and WBS Dictionary.
- The following are the processes in this knowledge area:
-> Plan Scope Management
-> Collect Requirements
-> Define Scope
-> Create WBS
-> Validate Scope
-> Control Scope
- The following are the most important outputs from this knowledge area:
-> Scope Management Plan – Planning
-> Scope Statement – Planning
-> WBS – Planning
- Project Scope includes product scope as well as processes followed and interim deliverables created as part of these processes.

Match the Following


1. Collect Requirements - a. Scope Statement
2. Define Scope - b. Customer Acceptance
3. Create WBS - c. Scope Management Plan
4. Plan Scope Management - d. WBS Dictionary
5. Validate Scope - e. Work Performance Information
6. Control Scope – f. Requirements Traceability Matrix

Match the Following (Answers)


1. Collect Requirements - f. Requirements Traceability Matrix
2. Define Scope - a. Scope Statement
3. Create WBS - d. WBS Dictionary
4. Plan Scope Management - c. Scope Management Plan
5. Validate Scope - b. Customer Acceptance
6. Control Scope – e. Work Performance Information

Match the Following


1. Plan Schedule Management - a. Activity Relationships
2. Define Activities - b. Project Schedule
3. Sequence Activities - c. Activity List
4. Estimate Activity Resources - d. Activity Durations
5. Estimate Activity Durations - e. Schedule Baseline
6. Develop Schedule – f. Resource Count

Match the Following (Answers)


1. Plan Schedule Management - e. Schedule Baseline
2. Define Activities - c. Activity List
3. Sequence Activities - a. Activity Relationships
4. Estimate Activity Resources - f. Resource Count
5. Estimate Activity Durations - d. Activity Durations
6. Develop Schedule – b. Project Schedule